ISABELA SOLAR POWER PROJECTTesting & Commissioning Dashboard
TotalEnergiesNextnorthSan Ignacio Energy Resources Development CorporationGHD

PROJECT CONTROL / T&C

Commissioning control board

Read-only progress view for owners and OE. Personnel and underlying test records are not published.

Tracker snapshotUpdated 2026-09-30 16:30:26 · refreshes every 60s

Equipment quantity

23,751

PV scope registered

Test instances

139,681

Across active test packages

Passed

13

Verified test results

Retest

1

Requires close-out

CURRENT POSITION

PV testing progress

0.01%
139,656Pending
11In progress
13Passed
1Retest

WORK PACKAGE DETAIL

Testing activity summary

5 active packages
Testing activityCodeEquipmentTest instancesPendingPassedProgress
Solar Cable TestingPV_DC22,464134,784134,7840
0.00%
LVAC Cable TestingPV_LV1,0734,2924,2911
0.02%
MVAC Cable TestingPV_MV371118712
10.81%
Fiber Optic Cable TestingPV_FOC1404204200
0.00%
Grounding System TestingPV_GND3774740
0.00%

INDEPENDENT TEST DETAIL

Progress by test item

Select a work package to review each individual test result.

18 test items
PV_DC

Solar Cable Testing

6 independent tests
VM

V&M

0.00%
22,464Pending
0In progress
0Passed
0Retest

0 of 22,464 passed

IR

IR Test

0.00%
22,464Pending
0In progress
0Passed
0Retest

0 of 22,464 passed

POL

Polarity Test

0.00%
22,464Pending
0In progress
0Passed
0Retest

0 of 22,464 passed

CONT

Continuity Test

0.00%
22,464Pending
0In progress
0Passed
0Retest

0 of 22,464 passed

VOC

Voc

0.00%
22,464Pending
0In progress
0Passed
0Retest

0 of 22,464 passed

ISC

Isc

0.00%
22,464Pending
0In progress
0Passed
0Retest

0 of 22,464 passed